Peachtree City has closed bidding on an overhaul of its police headquarters and a companion training facility that would also house an Emergency Operations Center — a project that leans on FEMA grant money and a delivery method designed to lock in costs before construction begins.
The city issued RFP No. 27-101PPD on September 10, 2026, seeking a Construction Manager at Risk (CMAR) for two adjacent public-safety buildings totaling about 35,005 square feet. Proposals were due October 15, 2026, at 3:00 PM, and the city's bid portal now lists the solicitation as closed, according to peachtree-city.org.
The scope spans two distinct sites. The existing Police Headquarters at 350 GA-74 is a single-story, 14,090-square-foot building slated for renovation. A separate two-story, 20,915-square-foot structure at 102 Gutherie Way — described as an existing facility — would be refurbished into a combined Police Training Facility and Emergency Operations Center. The two sites are near each other, with the training facility providing space for material storage and site logistics, according to the RFP published on governmentcontracts.us.
Architectural and engineering services are being handled by Goodwyn Mills Cawood, based in Atlanta. The city's project manager contact is Tim Symonds of Morgan Mill Consulting, according to the RFP.
Because the project is partially funded by a FEMA grant, the procurement follows federal competitive-proposal rules under 2 CFR 200.320(d). That means the winning contractor must comply with a range of federal requirements — including suspension and debarment checks, domestic preference for U.S.-made materials such as steel and cement, and affirmative steps to consider small, minority, women-owned, and veteran-owned businesses as subcontractors, according to the RFP text.
The CMAR delivery method — Construction Manager at Risk — is notable for how it shifts financial exposure. Under CMAR, the selected firm works alongside the design team during planning, then commits to a Guaranteed Maximum Price before construction starts, taking on the risk of cost overruns beyond that ceiling. It is a common approach for public projects where owners want cost certainty and early contractor input on constructability.
A mandatory pre-proposal conference and site walkthrough was held September 30, 2026, at the Gutherie Way training facility. Contractors were required to send a representative to both sites. Questions were accepted through October 6, with a final addendum issued by October 8, according to the RFP. Sealed proposals were to be delivered in person to City Hall at 151 Willowbend Road — faxed or emailed submissions were explicitly not accepted.
No public information on which contractor was selected, what Guaranteed Maximum Price was negotiated, or the current construction timeline has appeared in available sources. The next public milestone to watch for is a formal contract award announcement from the city.
Why it matters — Peachtree City residents and local contractors should watch for a contract award announcement that will reveal who will rebuild the city's core public-safety infrastructure — and how federal disaster-preparedness dollars are being spent.
⚠ Not yet confirmed
- Estimated construction cost is approximately $6 million
- Project scope includes interior and MEP upgrades, security enhancements, and evidence areas at Police HQ
- roughly $6 million overhaul
- The project's estimated construction cost is approximately $6 million, according to govtribe.com.
Reported by georgiabids.net, govcb.com, peachtree-city.org, govtribe.com, governmentcontracts.us
Where this comes from
Written by Papalocal's AI from these outlets' reporting. It can miss or misread things; the outlets are the record.