Peachtree City's police headquarters is getting a makeover — and city staff have picked who they want running it. Staff are recommending MEJA Construction as the construction manager for a renovation project that spans the police station, a new training facility, and the city's emergency operations center, with total project costs estimated at $8 million. The City Council votes on the selection Thursday, Nov. 19, at 6:30 p.m. in the Frances Meaders Council Chambers at City Hall, 151 Willowbend Road.
If approved, MEJA's fees are estimated at $346,500. That breaks down as no charge for the design phase, $256,500 for general conditions, and an overhead-and-profit fee of 1.5% — which comes to $90,000 on an estimated $6 million construction cost, according to a memo from Police Chief Janet Moon and three other officials.
The city used a 'construction manager at risk' process, a contract structure in which the firm works alongside designers on cost estimates first, then commits to build the project for an agreed maximum price. The city solicited proposals in September, according to bid records.
Three firms were evaluated on a five-point scale. MEJA did not score highest overall — it ranked below Hogan on experience and staff — but it proposed the lowest price. The memo from Moon and colleagues recommends MEJA on the strength of that pricing. The council will still need to see and approve a guaranteed maximum price before any construction begins.
The physical scope is substantial: renovation of the existing police headquarters — covering offices, mechanical and electrical upgrades, security systems, evidence areas, and the lobby — plus conversion of an existing building into a police training facility and emergency operations center, according to bid documents.
In October, the council moved $6 million from reserves to fund the work. The finance director put the all-in cost at $8 million. The memo says the money for MEJA's management fees is already in the fiscal year 2027 budget. The timeline has moved faster than expected: at the Nov. 5 work session, the project manager told the council a contractor recommendation would come in December. It arrived three weeks early.
Thursday's agenda is packed beyond the police station vote. The council will also consider a new 'Competitive Performance Plan' for city employees — a merit-raise system that would allow workers with at least 12 months of service to earn raises of 1% to 3% based on annual performance reviews ranked within their division. City Manager Justin Strickland told the council Nov. 5 that the existing Career Development Plan was tied to education and certifications rather than performance, and did not cover all employees. Staff say the new plan fits within the current salary budget and the city's 10-year financial model without requiring a millage rate increase.
Also on the agenda: a discussion — not a vote — on whether to authorize staff to study allowing backyard archery practice. Council member Michael Polacek requested the item after a resident noted that city code permits bow hunting on private property with proper state licenses but bans archery practice. Current city code, Section 50-19, prohibits firing an arrow within city limits except for hunting, self-defense, or at a council-approved archery range. Polacek has said the Police Department may need to weigh in before any ordinance change moves forward.
The council will also return to a design question for the new Kedron Aquatic Center building: what to do about 24 windows that will need tinting to control glare and heat, according to Recreation Director Harold Layton. The item is listed for discussion with no staff recommendation yet.
Why it matters — A council vote Thursday will determine who manages an $8 million overhaul of Peachtree City's core public safety facilities — and the same meeting will shape city employees' pay and potentially open a new debate over backyard archery.
⚠ Not yet confirmed
- The project is partially funded by a FEMA grant
- specific pre-bid meeting date of September 30 and proposals due October 15
- exact square footage figures for the buildings (14,090; 20,915; 35,005)
Reported by peachtreecitydaily.com, constructionbidsource.com, govtribe.com, bidbanana.thebidlab.com, georgiabids.net
Where this comes from
Written by Papalocal's AI from these outlets' reporting. It can miss or misread things; the outlets are the record.